Mercer Corridor Project: Fairview Ave. N fully re-opens to two-way traffic on Saturday, March 9th, final stage of Mercer East to begin

The following is from an SDOT email that came out on Monday, Feb 25th:
SDOT announces a milestone for the Mercer Corridor Project with the full re-opening of Fairview Ave. N to two-way traffic on Saturday, March 9, weather permitting. The re-opening of Fairview Ave. N is a pivotal part in the completion of the East Phase of the Mercer Corridor Project and marks the transition to Stage 4 - the final stage of Mercer East construction.
Since August, 2012, Fairview Ave. N has been restricted to one northbound lane between Harrison St. and Valley St. as crews complete work including undergrounding of electrical distribution, transmission and communication lines, replacement of storm drainage systems, widening Fairview Ave. N between Republican St. and Valley St., installation of new pavement, sidewalks, signals, lighting, signage and landscaping.
The newly re-opened Fairview Ave. N will feature two northbound lanes and two southbound lanes between Republican St. and Mercer St., with two dedicated right turn lanes onto the I-5 on-ramps, a left turn lane onto westbound Mercer St. and one through lane at the intersection of Mercer St. Southbound travelers on Fairview Ave. N will now have the option to continue south on Fairview and connect to Mercer St. with two dedicated left-turn lanes onto the I-5 on-ramps in addition to options for southbound travel towards City Center.
Lane Restrictions on Mercer Street the Evening of Friday, March 8
In preparation for fully re-opening Fairview Ave. N to traffic, Mercer St. will be restricted to two lanes in each direction beginning at 8:00 p.m. on the evening of Friday, March 8 through the morning of Saturday, March 9, as crews perform final signal work at the intersection of Fairview Ave. N and Mercer St. Two westbound lanes on Mercer St. will remain open from the I-5 off-ramps at Mercer St. to Boren Ave. N and two eastbound lanes will remain open from Boren Ave. N to the I-5 on-ramps. Uniformed police officers will be positioned in the intersection of Mercer St. and Fairview Ave. N to facilitate traffic flow.
Following signal work at the intersection of Fairview Ave. N and Mercer St., Fairview Ave. N will re-open to traffic in its final configuration on Saturday, March 9. Traffic engineers will remain onsite on Saturday to monitor traffic flow and adjust signal timing as necessary.
Final Stage of Mercer East to begin Saturday, March 9
The re-opening of Fairview Ave. N is a major milestone for the Mercer Corridor Project and signifies the transition into Stage 4-the final stage of Mercer East construction. Beginning Saturday, March 9, Valley St., Terry Ave. N, Westlake Ave. N and Broad St. will be restricted in the following areas:
· Valley St. will restricted to one westbound lane between Fairview Ave. N and Terry Ave. N and closed to traffic between Terry Ave. N and Westlake Ave. N
· Westlake Ave. N will be restricted to one northbound lane between Valley St. and Aloha St.
· Broad St. will be closed between Westlake Ave. N and 9th Ave. N
· Northbound Terry Ave. N will be restricted to local access only between Mercer St. and Valley St.
· Access to Lake Union Park will be maintained via Fairview Ave. N and Valley St.
This temporary configuration will be maintained during Stage 4 of construction as crews complete work on Valley St., Broad St., Terry, Westlake and 9th avenues. Work during Stage 4 includes undergrounding of electrical distribution and communication lines; replacement or relocation of water, sewer, and storm drainage systems; relocation of gas lines; and the installation of new pavement, sidewalks, signals, lighting, signage, bike lanes, landscaping and urban design features. Stage 4 is anticipated to be completed in July.
Please note the re-opening of Fairview Ave. N is dependent on weather and subject to cancelation.
Detour information available for Stage 4 construction
Detour maps illustrating the re-opening of Fairview Ave. N as well as restrictions on Valley St., Westlake Ave. N and Broad St. are available online for motorists at: www.seattle.gov/Transportation/ppmp_mercer.htm. Pedestrian and bicycle detour maps will be available online prior to Fairview Ave. N re-opening to traffic.
Impacts to transportation services
During Fairview Ave. N construction, Metro Transit rerouted several bus routes via Eastlake Avenue. As plans are finalized, Metro will alert riders with a specific date when bus service will move back to Fairview Avenue N. More information can be found here: http://metrofutureblog.wordpress.com/2012/08/13/routes-70-71-72-73-83-and-309-to-be-rerouted-aug-24-for-fairview-ave-n-construction/
Contacts and Information
If you have comments or questions about the Mercer Corridor Project, please contact us at:
Project and Construction Information
24-hour Construction Hotline: (206) 419-5818
For more information about project purpose, benefits, and other information, visit our website at www.seattle.gov/Transportation/ppmp_mercer.htm.
If you need this information translated, please call (206) 733-9990.
Si necesita traducir esta informaciĆ³n al espaƱol, llame al (206) 733-9990.

No comments:

Post a Comment